PROJECT NAME
263 MIP
LOCATION
Sipcot Perundurai
TYPE OF STRUCTURE
A type
USAGE
Battery Lead Recycling Unit
Tonnage
0
MT
Area
0
Sq.Mtrs
0
Mtrs Span
0
Mtrs Height
Span / Height
DESCRIPTION
- The project was executed for M/s Metstar Industries
CHALLENGES FACED
- We completed this proposed project within a critical deadline as per the client's request. So the structure installation was a significant challenge. This site had a shortage of space for crane movement bounded by pits and intermediate columns for machine floors.
RISK MANAGEMENT
- Later, after installing the structure, there was a cut-out requirement for the chimney at roof level. But there was an interruption of 400mm, so the Rafter was relocated using a jack beam support for the specified location.